New transformer at Buġibba Distribution Centre will strengthen capacity by 50%

Published by
The Malta Business Weekly

Enemalta’s investment at the Buġibba Distribution Centre is set to reinforce the centre’s capacity by 50%, thanks to the installation of a brand new transformer, delivered this week, the government said Thursday. With the project on track to be completed by the end of this month, the extension will strengthen electricity services to about 25,000 consumers in this region.

The DC, connected to multiple substations, distributes electricity services to consumers in Qawra, St Paul’s Bay, and Buġibba.

During a site visit, Energy Minister Miriam Dalli and Enemalta executive chairperson Ing. Ryan Fava expressed their gratitude to the dedicated team of engineers and technicians. Enemalta is currently undergoing continued and coordinated efforts toward strengthening the national grid on multiple levels.

“The energy demand in this area is on the rise, particularly during the summer months. As part of the reinforcement works that Enemalta is carrying out across Malta and Gozo, we have also scheduled the strengthening of this area. The installation of an additional transformer translates into both an increased capacity as well as providing Enemalta with further resilience as the demand increases,” Minister Miriam Dalli said, thanking workers for their efforts.

Ing. Ryan Fava explained the new power transformer carries a 30MVA capacity. This will help in better distribution of our demand in these areas especially in peak demand periods. Enemalta will also see the extension of the remote operation and monitoring for the new transformer, that will allow engineers to monitor and remotely control the new transformer from Enemalta’s control room in Marsa.

Enemalta is actively working on the development of new distribution centres in Naxxar and Siġġiewi, which are currently in advanced procurement and planning stages. In December, Enemalta issued a call for offers to upgrade the distribution centre in Msida with new switchgear, transformers, and other equipment. Enemalta is also planning to extend the distribution centre in St. Andrew’s, Pembroke.

In a separate project launched in December, Enemalta laid more than 70km of new underground cables in different localities to increase new alternative connections that will reduce network disruptions while facilitating quicker restoration of service when such difficulties arise.

The Malta Business Weekly

In 1994, the Malta Business Weekly became the first newspaper fully dedicated to business. Today this newspaper is a leader in business and financial news. Together with the launch of the MBW newspaper, the company started organising various business breakfasts to discuss various current issues that were targeting the business community in Malta.

Recent Posts

MFSA warns public of fraudulent companies misusing licensed entities’ details

The Malta Financial Services Authority (MFSA) has issued warnings against several fraudulent companies exploiting the…

1 day ago

Prime Minister visits Gozitan businesses which thrived after receiving support

During a visit to Gozo, Prime Minister Robert Abela toured two Gozitan businesses that have…

1 day ago

MDA calls for reform to ensure ‘fairness and accountability’ in magisterial Inquiries

The Malta Developers Association (MDA) on Saturday expressed serious concerns about the practice of implicating…

1 day ago

BOV Bugibba and Ħal Luqa branches reopen with modern upgrades

Branch in Ħaż-Żebbuġ closes for refurbishment Following weeks of intensive work, the Bugibba and Ħal…

1 day ago

Gozo’s economic growth must continue to result in common good and identity preservation, PM says

Prime Minister Robert Abela said that Gozo is an example of how economic growth must…

1 day ago

€1.6 billion to be invested in pensions and social benefits throughout 2025

€1.6 billion is set to be spent on pensions and social benefits throughout the calendar…

2 days ago