Production of Malta-Sicily second interconnector in progress in Norway and US

Published by
The Malta Business Weekly

Production works on the second electricity interconnector cable between Malta and Sicily are well underway. Current project activity related to the submarine cable is focused on two key areas: fibre optic production at Nexans’ facility in Rognan, Norway, and high-voltage subsea cable manufacturing at the company’s plant in Charleston, South Carolina.

The production of the fibre optic elements has commenced, following the signing of the contract between the Maltese Government and Nexans. Nexans is a global leader in the design and manufacturing of cable systems and services, specializing in the offshore wind market and subsea interconnectors. The fibre optic elements will be integrated into the high-voltage subsea cable. This phase of the project is taking place at Nexans’ facilities in Rognan, Norway, and marks another significant milestone in the strategic infrastructure project.

Approximately half of the 104km total fibre optic cable length required, has already been produced, tested, and shipped to Nexans’ factory in Charleston (SC), USA. The Charleston facility is responsible for manufacturing and testing high-voltage cables.

This significant update comes after the formal contract signing in Malta in April of this year.  This €300 million project has been designated as an ‘Operation of Strategic Importance’ due to its significant contribution to the achievement of Malta’s priorities for the 2021-2027 ERDF Programme of the European Union.  The ERDF funding allocated to the Project amounts to €165 million and will cover more than half of the total investment costs, highlighting its importance to regional and national energy strategies. Once completed, the 245kV submarine cable will double Malta’s connectivity to the European energy grid.

The second interconnector will not only increase the security of the electrical supply but will also lead to increased investment in renewable energy, which will help Malta better handle the intermittent nature of green sources like offshore wind and solar. According to the project’s cost-benefit analysis, 13.5 million tonnes of CO2 emissions will be reduced, enhancing its significance in Malta’s long-term decarbonisation strategy.

Project information can be found at: https://icm.mt/projects/ 

The Malta Business Weekly

In 1994, the Malta Business Weekly became the first newspaper fully dedicated to business. Today this newspaper is a leader in business and financial news. Together with the launch of the MBW newspaper, the company started organising various business breakfasts to discuss various current issues that were targeting the business community in Malta.

Recent Posts

BOV commences share buyback programme

First credit institution in Malta to introduce this scheme Bank of Valletta is pleased to…

15 hours ago

Malta International Airport applies to create new dedicated Y-plate lane, reconfigure car park

The Malta International Airport has filed a planning application to reconfigure and expand its car…

15 hours ago

Nearly 1,300 final deeds of sale registered in July – NSO

In July, the number of final deeds of sale and promise of sale agreements relating…

3 days ago

Government launches irrigation water aid scheme for farmers

Minister for Agriculture, Fisheries and Animal Rights Anton Refalo has launched an aid scheme for…

3 days ago

Before the MEP elections it was the caravans, now it’s agricultural land!

Last week I had to write about Malta’s latest agricultural land law. However, I gave…

2 weeks ago

The mother of all pyrrhic victories

The recently announced EU-US trade deal, while presented as a diplomatic success, is in reality…

2 weeks ago